In this research project, the optimal design and design evaluation of a hybrid microgrid based on solar photovoltaics, wind turbines, batteries, and diesel generators were performed.

The conventional grid-tied mode was used in addition to dispatch strategy-based control.

The study’s test location was the loads in the Electrical, Electronic and Communication Engineering (EECE) department at Pabna University of Science and Technology (PUST), Pabna, Bangladesh. DIgSILENT PowerFactory was employed to determine the power system-based behaviors (electrical power, current, voltage, and frequency) of the proposed hybrid system, while a derivative-free algorithm was used for the expense, optimal size, and emission assessments.

While developing the microgrid, load following (LoF) and cycle charging (CyC) control were employed.

The microgrid is supposed to have a 23.31 kW peak load requirement. The estimated microgrid’s levelized cost of energy (LE), its net present cost (NC), its operating cost, and its annual harmful gas emissions were estimated in this work. Additionally, since the microgrid is grid-connected, the amount of energy output that might be exported to the grid was also estimated, which will potentially increase during blackouts.

The power system responses found in this study ensure that the various microgrid components’ voltage, frequency, current, and power outcomes are steady within the designated range, making the microgrid practical and robust.

Read more

 

The latest news

Why EIT’s New Applied Research Programs Could Be Your Next Big Academic Move

What if the next stage of your engineering journey is not about learning more, but doing more with what you already know? Many students and...
Read more

Degrees Matter, Only If They Can Prove You Can Do the Job

What does it really mean to be ‘ready’ in engineering today – knowing the theory, or being able to prove you can apply it? In...
Read more

Asset Integrity in Safeguarding Engineering Projects

What makes an engineering project successful? Is it achieving project timelines, staying within cost targets, and meeting specific design specifications - or ensuring sustained performance...
Read more
Engineering Institute of Technology